PMP®高頻錯題(17)
高頻錯題(17)
1、 [單選] 項目經理向所有相關方發(fā)送定期狀態(tài)報告,報告內容包括項目成就列表,即將完成的目標和目前的挑戰(zhàn)。但是,一些相關方仍抱怨說他們不了解項目的狀態(tài)。項目經理應該怎么做?
A project manager sends out regular status reports to all stakeholders with bulleted lists of project accomplishments,upcoming objectives,and current challenges.However,some stakeholders still complain that they do not understand the project's status.What should the project manager do?
A:聯(lián)系這些相關方以了解他們擔心的問題,并在實施變更之前遵循變更請求過程
Contact those stakeholders to understand their concerns, and follow the change request process prior to implementing changes
B:向這些相關方分布一些新的,更詳細的狀態(tài)報告
Distribute a new,more-detailed status report to those stakeholders
C:要求這些相關方審查溝通管理計劃并向他們提供最新的狀態(tài)報告
Ask those stakeholders to review the communications management plan and provide them with an updated status report
D:與這些相關方和項目團隊開會,以提供更詳細的項目狀態(tài)更新
Meet with those stakeholders and the project team to provide a more-detailed project status update
正確答案:C 你的答案:A
解析:溝通管理計劃包含了相關方的溝通需求,確定了需要溝通的信息、接收信息的人員或群體,包括他們的需要、需求和期望。項目經理定期發(fā)送狀態(tài)報告,這是在溝通管理計劃確定好的,相關方對此有抱怨,首先要求這些相關方審查溝通管理計劃,確認之前達成的溝通共識,也許這些相關方在溝通計劃里就是不需要知道狀態(tài)的,所以首先審查。
2、 [單選] 項目經理已經完成識別相關方的工作。之前,由于沒有對項目經理和相關方的影響力或職權方面規(guī)定區(qū)別,項目經理在管理相關方方面有困難,在相關方登記冊中需要包含哪一些信息?
A project manager has completed the identification of stakeholders.Previously,the project manager had difficulty managing stakeholders because no distinctions were made among them regarding influence or authority. What information needs to be included in the stakeholder register?
A:新相關方的變更請求
Change requests for new stakeholders
B:相關方效益管理計劃
Stakeholder benefits management plan
C:相關方參與計劃
Stakeholder engagement plan
D:相關方分類
Stakeholder classification
正確答案:D 你的答案:C
解析:說明解析:PMBOK(6)P514-13.1.3.1識別相關方-相關方登記冊。包括相關方分類。選項A:新相關方的變更請求不包括在相關方登記冊中。選項B:相關方效益管理計劃不包括在相關方登記冊中。 選項C:相關方參與計劃確定用于促進相關方有效參與決策和執(zhí)行的策略和行動,不包括在相關方登記冊中。
3、 [單選] 在一個項目接近完工時,發(fā)起人要求承包商改變已安裝的照明以符合新標準。承包商應該怎么做?
As a project nears completion,the sponsor asks the contractor to change the installed lighting to comply with a new standarWhat should the contractor do?
A:審查工作并提交一份顯示工作已完成的報告
Review the work and submit a report showing that work is already complete.
B:請求延長工期并提交變更請求以完成工作
Request a schedule extension and submit a change request to complete the work.
C:與發(fā)起人一起檢查新規(guī)定,然后提交變更請求
Examine the new regulation with the sponsor and then submit a change request.
D:評估成本和進度影響,然后向項目經理提交變更請求
Evaluate the cost and schedule impact and then submit a change request to the project manager.
正確答案:C 你的答案:D
解析:本題如果沒有提到新標準,就直接選D了。由于發(fā)起人變更的理由是符合新標準,應首先了解新標準是什么,才好進行變更,C 優(yōu)先于 D。
4、 [單選] 在一個工廠的項目建議書談判期間,客戶通知項目經理需要進行一項變更來提高性能。項目經理該怎么做?
During project proposal negotiations for an industrial plant, the customer informs the project manager that a change is required to improve performance. What should the project manager do?
A:讓項目發(fā)起人增加額外資金
Ask the project sponsor for additional funding.
B:征求高級管理層的建議
Call senior management for advice.
C:更新工作分解結構(WBS)
Update the work breakdown structure (WBS).
D:修訂風險應對計劃
Revise the risk response plan.
正確答案:B 你的答案:D
解析:參考答案:B。 解析:項目早期(啟動之前),客戶想要變更內容,應優(yōu)先高級管理層(包括發(fā)起人)的參與。
5、 [單選] 當面臨缺乏歷史數(shù)據時,項目經理會做出各種假設,許多這些假設被證明是不正確的,至少引發(fā)了一個高影響的問題 若要避免這個問題,項目經理應該事先使用什么?
When faced with a lack of historical data a project manager makes various assumptions.A number of these assumptions prove incorrect triggering at least one high-impact issue. What should the project manager have used to avoid this?
A:顯性知識
Explicit knowledge
B:事業(yè)環(huán)境因素
Enterprise environmental factors
C:專家判斷
Expert judgement
D:組織過程資產
Organizational process assets
正確答案:B 你的答案:C
解析:參考答案:B 解析:pmbok6的78頁4.1.1.3事業(yè)環(huán)境因素:缺少歷史信息是現(xiàn)實情況,也是項目經理無法影響的客觀因素。
6、 [單選] 在啟動階段,項目經理意識到主要里程碑與范圍不一致,這可能導致誤解,項目經理下 一步應該怎么做?
During the initiating stage,a project manager realizes that main milestones are misaligned with the scope,which may cause misinterpretation.What should the project manager do next?
A:在項目管理計劃中詳細說明范圍和可交付成果
Detail the scope and deliverables in the project management plan.
B:提出一項變更請求,以修改范圍和可交付成果
Submit a change request to modify the scope and deliverables.
C:在項目章程中規(guī)定范圍和可交付成果
Specify the scope and deliverables in the project charter.
D:在問題日志中記錄誤解范圍和可交付成果的可能性
Document the possibility of scope and deliverables misinterpretation in the issue log.
正確答案:C 你的答案:D
解析:參考答案:C。解析:PMBOK(6)P81,題目中處于項目啟動過程,還未進行到規(guī)劃階段和監(jiān)控過程,故不選A和B。根據項目章程包含高層級項目描述、邊界定義以及主要可交付成果和總體里程碑進度計劃 ,故選C。
————————————————
版權聲明:本文為CSDN博主「LK_Tracking」的原創(chuàng)文章,遵循CC 4.0 BY-SA版權協(xié)議,轉載請附上原文出處鏈接及本聲明。
原文鏈接:https://blog.csdn.net/weixin_40039983/article/details/108405385
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
相關內容